sort by

AltaLink – 895s Suffield

Location:
Suffield, AB
Year:
2023
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
25kV Switchgear Building
25kV protections & merging unit additions (IEC 61850)
Demolition of existing 25kV protections and breakers
SCADA and LAN Equipment upgrades

BC Hydro – Queensborough Substation

Location:
New Westminster, BC
Year:
2022
Client:
BC Hydro
Scope of Work:
Breaker Commissioning
Relay Commissioning
SCADA Commissioning
Potential Transformer Commissioning

Iconic Power Systems – Shell 304s Battery Bank Replacement

Location:
Clearwater, AB
Year:
2022
Client:
Iconic Power Systems
Partnered with:
AltaLink
Scope of Work:
Installation of Temporary 125VDC Battery Bank to maintain DC system and services while new battery bank was installed, tested and commissioned

Iconic Power Systems – Garden Plains Wind Collector Substation

Location:
Drumheller, AB
Year:
2022
Client:
Iconic Power Systems
Scope of Work:
240 kV/34.5kV Collector Substation240kV/34.5kV Breaker, CT, CVT, Disconnect, Capacitor Bank Commissioning
Transformer, Bus, Feeder, Capacitor Bank Protection Testing
SCADA Commissioning

Iconic Power Systems – Blue Earth Handhills Wind Collector Substation

Location:
Drumheller, AB
Year:
2022
Client:
Iconic Power Systems
Scope of Work:
138kV/34.5kV Collector Substation
138kV/34.5kV Breaker, CT, CVT, Disconnect, Capacitor Bank Commissioning
Transformer, Bus, Feeder, Capacitor Bank Protection Testing
SCADA Commissioning

Iconic Power Systems – Suncor Coke Boiler Replacement Project

Location:
Suncor Base Plant, Fort MacMurray, AB
Year:
2022
Client:
Iconic Power Systems
Scope of Work:
Gas Removal and Salvage of Qty-8 72kV SF6 Dead Tank Breakers
Testing and Complete Replacement of Qty-8 72kV SF6 Dead Tank Breakers

Rodan – Revenue Meter Instrument Transformer Commissioning

Location:
Medicine Hat, Coaldale, High River, Vulcan, Monarch, Wildwood
Year:
2022
Client:
RODAN Energy Solutions
Scope of Work:
240kV CT/PT Combination IT Commissioning

Black & McDonald – Inuvik High Point Wind

Location:
Inuvik, NWT
Year:
2022
Client:
Iconic Power Systems
Partnered with:
PCL Construction
Scope of Work:
Relay Commissioning
Switchgear Commissioning
Transformer Commissioning
MV Cable Terminations and Testing

AltaLink – 89s Ellerslie Urgent CT Replacements

Location:
Edmonton, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Demo 240kV CTs
Commission new replacement 240kV CTs

AltaLink – 2022 ACC Visibility Program (68s Willesden Green, 420s Broadmoor, 434s Stony Plain, 895s Suffield, 964s Pigeon Lake)

Location:
Alberta
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Modify Transformer alarms to SCADA
Add 25kV Recloser supervisory control and status

AltaLink – 247s Piper Creek, 635s Rose Valley

Location:
Red Deer AB / Keephills, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Modify security alarming

AltaLink – Michichi Solar DER RAS

Location:
Jarrow, AB / Irma, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Install and commission RAS

AltaLink – 895s Suffield

Location:
Suffield, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
25kV Switchgear Building
25kV protections & merging unit additions (IEC 61850)
Demolition of existing 25kV protections and breakers
SCADA and LAN Equipment upgrades

AltaLink – 2022 Fault Reporting Program (198s Blackfalds, 262s Rocky Mountain House, 397s Benbow & 602s Cold Creek)

Location:
Alberta
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138kV protection setting changes
LAN / SCADA changes and testing for implementation of fault location and type reporting to the AltaLink control center via SCADA

AltaLink – 250P Bighorn

Location:
Rocky Mountain House, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
SCADA Upgrade

AltaLink – 525s Carseland

Location:
Carseland, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138/25kV Transformer Replacement
138kV Transformer protection upgrades
138kV MOD upgrade
SCADA and LAN equipment upgrade

AltaLink – 103s Goose Lake Urgent CT Repair

Location:
Pincher Creek, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Demo 240kV CT
Commission new replacement 240kV CT

AltaLink – 64s East Crossfield

Location:
Crossfield, AB
Year:
2022
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
Demo 25kV Breaker line protection, breaker control and recloser
Install and commission new 25kV breaker line protection/control
Module install and commission new 25kV line PT

AltaLink – Carseland Transformer Upgrade

Location:
Carseland, AB
Year:
2022
Client:
AltaLink
Scope of Work:
Demo existing power transformer
Demo existing protection devices
Commission new power transformer
Commission new protection devices

Iconic Power Systems – Tesla Battery Bank

Location:
Various locations across Alberta
Year:
2022
Client:
Iconic Power Systems
Partnered with:
PCL Construction
Scope of Work:
Switchgear Testing
Relay Testing
Transformer Testing
Cable Testing

Iconic Power – Conrad Solar

Location:
Conrad, AB
Year:
2022
Client:
Iconic Power Systems
Partnered with:
PCL Construction
Scope of Work:
Recloser commissioning
Commission all SCADA devices
Installation/setup of fault indicators

BC Hydro – Bridge River T4 Replacement

Location:
Seton Portage, BC
Year:
2022
Client:
BC Hydro
Scope of Work:
Relay Settings modification and testing
Wiring isolation/re-connection
Function of transformer devices
CVT replacement

BC Hydro – Site C Commissioning

Location:
Fort St. John, BC
Year:
2022
Client:
BC Hydro
Scope of Work:
Relay Commissioning
Switchgear Commissioning
Integration of multiple systems

BC Hydro – North Vancouver Island Maintenance

Location:
Multiple sites across Vancouver Island, BC
Year:
2022
Client:
BC Hydro
Scope of Work:
Relay Maintenance
Meter Maintenance
NERC Testing/Validation

Enmax – Crossfield Energy Center Facilities

Location:
Crossfield, AB
Year:
2022
Client:
Enmax
Scope of Work:
15kV Switchgear and Breaker Maintenance
Oil and Gas Analysis
Functional Testing of Protection EquipmentTransformer Testing

Enmax – Calgary Energy Center Maintenance

Location:
Calgary, AB
Year:
2022
Client:
Enmax
Scope of Work:
Ground Resistance Testing
Breaker Testing
Bus Duct Inspections
Neutral Grounding Equipment

RESA Power – Substation Feeder Upgrade Support

Location:
Granbury, TX
Year:
2022
Client:
RESA Power
Scope of Work:
35kV/138kV Breaker Testing
CT/PT Testing
Surge Arrestors
Transformer Loading for transport

Saturn Power – Bruce Power – Transformer Testing

Location:
Ontario
Year:
2022
Client:
Saturn Power
Scope of Work:
Transformer Inspection
Oil Sampling
Maintenance Testing
Transformer Loading for transport

BC Hydro – Maintenance

Location:
North Vancouver Island Sub GLD, QLC, OYR.
Year:
2021
Client:
BC Hydro
Scope of Work:
Maintenance testing to bring micro-processor relays up to NERC compliance (SEL351, SEL421, SEL321)
Maintenance testing on micro-processor meters (ION and SEL)
Settings verification, changes, and testing
Maintenance testing on electro-mechanical relays (CO-5, CO-8, ECT)

ENMAX – Calgary Energy Center Maintenance

Location:
Calgary, AB
Year:
2021
Client:
Enmax
Scope of Work:
600v MCC and Breaker Testing
4160v Switchgear
Breakers
Contactors

Enmax – Crossfield Energy Centre Circuit Breaker Refurbishment

Location:
Crossfield, AB
Year:
2021
Client:
Enmax
Scope of Work:
600V Circuit Breaker Refurbishment
600V Breaker Testing
Replacement/Repair of Charging Motor Mechanism

AltaLink – 217s P&C support City of Red Deer

Location:
Provost, AB
Year:
2021
Client:
AltaLink
Scope of Work:
Upgrade of Existing T1 A protection
Addition of new T2B protection
Replacement of 138kV L2A Line protection
Associated SCADA changes

Enmax – Medium Voltage Cable Testing

Location:
Calgary, AB
Year:
2021
Client:
Enmax
Scope of Work:
Tan Delta and VLF Acceptance testing of newly installed
Medium voltage power cabling

AltaLink – 42s SCADA Major Upgrade

Location:
Calgary, AB
Year:
2021
Client:
AltaLink
Scope of Work:
Transition and cutover of existing D20 RTU SCADA system to a new redundant Beckwith SMP SG4250 RTU and data concentrator along with associated 2440 I/O status and control boards.
18 weeks of individually planned equipment outages along with detailed execution planning was required to accomplish the safe and reliable cut over of all existing station alarms and controls to the new SCADA system.
DNP modifications to existing 240kV Line protections for metering purposes.

AltaLink – Provost and Upgrades

Location:
Provost, Hayter, Kilarney Lake, Edgerton, Hansman Lake, Metiskow
Year:
2021
Client:
AltaLink
Partnered with:
Burns & McDonnell
Scope of Work:
138kV Dead Tank Breaker Additions
138kV Manual and Motor Operated Disconnects
138kV CVT Additions
138kV Protection upgrades, Line, Breaker fail, Buss

AltaLink – 2020 SRT/GRT Program – 29s Cascade, 67s Sterling, 135s Conrad, 151s Strathmore, 392s Black Diamond

Location:
Alberta
Year:
2020
Client:
AltaLink
Scope of Work:
Completion of SRT and GRT fall of potential testing
Using engineered profiles

AltaLInk – 415s Drywood Protection Upgrades

Location:
Provost, AB
Year:
2020-2021
Client:
AltaLink
Scope of Work:
Upgrade of Existing T1 A protection
Addition of new T2B protection
Replacement of 138kV L2A Line protection
Associated SCADA changes

Teric Power – TESLA Battery Energy Storage System

Location:
Raycroft, AB
Year:
2020
Client:
Teric Power
Scope of Work:
25kV Switchgear and Protection Testing
Pre-Commissioning, and Full Site Commissioning and Startup assistance for newly added Tesla MEGAPACK BESS system

AltaLink – 336s Fortis Area Upgrades Fincastle

Location:
Taber, AB
Year:
2020
Client:
AltaLink
Scope of Work:
Testing of new 138kV / 25kV Power Transformer
145kV LTB Circuit Breakers, HV Disconnects
and 25kV switchgear building
New Transformer, Breaker Fail, and Full Station

AltaLink – 19s Wabamun Breaker Replacements

Location:
Edmonton, AB
Year:
2020
Client:
AltaLink
Scope of Work:
138kV Dead Tank Breaker Replacements
69kV Surge arrestor replacements
240kV Strain Insulator replacements

AltaLink – 428s Namaka Protection and Substation Upgrades

Location:
Strathmore, AB
Year:
2020
Client:
AltaLink
Scope of Work:
Protection upgrades for the following:
138kV A & B Buss Diff Protections
138kV Line PN Upgrades Qty – 3
138kV/25kV T1 A & B PN Upgrades

Enmax – Crossfield Energy Center Facilities

Location:
Crossfield, AB
Year:
2020
Client:
Enmax
Scope of Work:
15kV Switchgear and Breaker Maintenance
Oil and Gas Analysis
Functional Testing of Protection Equipment
Transformer Testing

Altalink – Sync Check Protection Modifications *Various Locations

Location:
Southern Alberta
Year:
2020
Client:
AltaLink
Scope of Work:
Protection modifications to Sync Check Breaker close logic on various
240kV and 138kV transmission lines throughout southern Alberta

AltaLink – 510s Sunnybrook 500kV Transmission Line and Shunt Reactor Addition

Location:
Edmonton, AB
Year:
2019
Client:
AltaLink
Scope of Work:
500kV Breaker, Disconnects, Stand Alone CT, and Shunt Reactor Additions
New 500kV Line, Breaker Fail, Shunt Reactor
Synchronizer Packages, Associated SCADA changes
500kV HVDC testing and logic changes

TransAlta – Bushing replacement

Location:
Fort Saskatchewan, AB
Year:
2019
Client:
TransAlta
Scope of Work:
Testing of Generator Power Transformer
Testing of Bushings

TransAlta – Dow Chemicals

Location:
Fort Saskatchewan, AB
Year:
2019
Client:
TransAlta
Scope of Work:
HV Bushing Investigation
Doble Testing of Bushings

Altalink – Red Deer Scada Upgrade

Location:
Red Deer, AB
Year:
2019
Client:
AltaLink
Scope of Work:
Scada System upgrades
Installation and commissioning of hardened Ethernet switches
Updated HMI systems and installed/commissioned new alarm and control IEDs
for existing 25kV, 138kV and 240kV associated equipment

Altalink – Ellerslie Scada Upgrade

Location:
Edmonton, AB
Year:
2019
Client:
AltaLink
Scope of Work:
Scada System upgrades
Installation and commissioning of hardened Ethernet switches
Updated HMI systems and installed/commissioned new alarm and control IEDs for existing
25kV, 138kV and 240kV associated equipment

Altalink – CSC ICSS Controls *Multiple Sites

Location:
Southern, AB
Year:
2019
Client:
AltaLink
Scope of Work:
Cyber Security Implementation on Network Switches, protective relays
and RTU installation and modifications to existing RTUs
Preformed High Voltage Switching and Isolations

AltaLink – 42s Southwest Ring Road

Location:
Calgary, AB
Year:
2018
Client:
AltaLink
Partnered with:
Burns & McDonnell
Scope of Work:
Point on Wave controller new 138kV & 240kV U/G transmission lines
Line protection end to end testing,
Buss, Transformer modifications, protection upgrades
SCADA additions and testing.

AltaLink – 42s Substation

Location:
Calgary, AB
Year:
2018
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138kV & 240V transmission cable point on wave controller
138kV & 240V U/G transmission lines
Line protection end to end testing
Buss and transformer modifications

AltaLink – 510s Sunnybrook 40V Breaker Addition

Location:
Calgary, AB
Year:
2018
Client:
AltaLink
Partnered with:
Burns & McDonnell
Scope of Work:
480V Breaker Addition to existing Switchgear
Application of protection Settings
Final Testing and Comissioning

AltaLink – 320P Complete SCADA Upgrade / Replacement

Location:
Calgary, AB
Year:
2018
Client:
AltaLink
Scope of Work:
D20 SCADA system, Annunciator, Alarms, supervisory controls. SCADA
320P Substation until the entire substation complete.
Demolition of metering transducers and installation of new SCADA meters.
Demolition and cut over of old station LAN and IRIG-B clocks to new standard

BC Hydro – FNE Station Replacement Project

Location:
Surrey, BC
Year:
2018
Client:
BC Hydro
Partnered with:
AMEC BDR
Scope of Work:
60kV Line Protection replacements including Testing & Commissioning

Manitoba Hydro Bi-pole 3 Project 500kV HVDC

Location:
Winnipeg, MB
Year:
2018
Client:
Siemens
Partnered with:
Mortenson Construction
Scope of Work:
Equipment pre-commissioning for HVDC yard, 240kV AC filter banks,
DC Charger and UPS systems, and low voltage auxiliary power systems.
Coordination with construction to assist in the gas filling for HVDC voltage dividers.
Filling for HVDC voltage dividers.

AltaLink – 510s Sunnybrook 40V Breaker Addition

Location:
Calgary, AB
Year:
2018
Client:
AltaLink
Partnered with:
Burns & McDonnell
Scope of Work:
480V Breaker Addition to existing Switchgear
Application of protection settings
Final Testing and Commissioning

AltaLink – 63’s RATD project

Location:
Innisfail, AB
Year:
2017
Client:
AltaLink
Partnered with:
SNC Lavalin
Scope of Work:
Full Green Field Commissioning of Hazelwood Substation
Demo/Install of line/Transformer/Bus Protection in Remote Ends
Testing and Commissioning of all Major Equipment
Testing and Commissioning of all P&C and SCADA Equipment

AltaLink – 89s Complete SCADA Upgrade / Replacement

Location:
Ellerslie, AB
Year:
2017
Client:
AltaLink
Scope of Work:
SCADA system, Annunciator, Alarms, supervisory controls and analogs
Multiple Outages staged systematically to cut over 89S Substation
Demolition of mimic board and metering transducers, replacement of 240kV Airbreak control modules.
Installation of new SCADA meters.

Manitoba Hydro – KCS/RCS HVDC Equipment Commissioning

Location:
Keewatinohk, MB
Year:
2017
Client:
Manitoba Hydro
Partnered with:
Mortenson Construction
Scope of Work:
Full Testing and Commissioning of HVDC Auxiliary Systems
Full Testing and Commissioning of HVDC Yard Equipment

Manitoba – Keewatinohk AC Yard Pre-Commissioning

Location:
Keewatinohk, MB
Year:
2017
Client:
AltaLink
Partnered with:
SNC Lavalin
Scope of Work:
Full Green Field Pre-Commissioning of AC Yard
Testing of All Major Equipment in AC Yard
Testing of Two 13.8kV Switchgear Buildings
Testing of Three 600V OPC Buildings

AltaLink – 649s Full Metering Upgrade

Location:
Chapice Lake, AB
Year:
2017
Client:
AltaLink
Scope of Work:
Addition of Single Phase 138kV Metering PT to change existing
revenue metering scheme from a 2 PT Metering Method to
3 phase Metering Method.
Energization support – Load Readings / Phasing Checks

AltaLink – 352s Onoway 69kV Breaker Replacement

Location:
Onoway, AB
Year:
2017
Client:
AltaLink
Scope of Work:
Coordination with AML scheduling / AML Mobile Sub Crew/ Construction
and Commissioning for the installation of the Mobile Substation
Salvage of existing 69kV Bulk Oil breaker and installation of new Mitsubishi
69kV Dead Tank BKR.

Altalink – 395s SCADA Upgrade / Urgent Replacement

Location:
North Holden
Year:
2017
Client:
AltaLink
Scope of Work:
Urgent replacement/retrofit of failed of failed D20++ with a D20 EME

AltaLink – 65s High River 25kV Breaker Replacements

Location:
High River, AB
Year:
2017
Client:
AltaLink
Scope of Work:
Coordination with AML substation crews to assist in the P&C changes and
Equipment commissioning for the replacements of Qty - 4 25kV Outdoor Circuit Breakers.

AltaLink – 793s Complete SCADA Upgrade / Replacement

Location:
Horse Creek, AB
Year:
2017
Client:
AltaLink
Scope of Work:
Demolition and cut over of old D20 SCADA system, Annunciator, Alarms
& supervisory controls to new standardized SCADA system.
Multiple Outages staged systematically to cut over 793s Substation until the
entire substation and integration with IPL plant was complete.

AltaLink – 332s RATD Phase 3

Location:
Northern, AB
Year:
2017
Client:
AltaLink
Partnered with:
SNC Lavalin
Scope of Work:
Transmission line addition and lines swapped
Bus Protection upgrade
138kV dead tank breaker commissioning
Airbreak and Surge Arresters commissioning

AltaLink – 395s SCADA Upgrade / Urgent Replacement

Location:
North Holden
Year:
2017
Client:
AltaLink
Scope of Work:
Urgent replacement/retrofit of failed of failed D20++ with a D20 EME

BC Hydro – BMT Load Capacity Increase Project

Location:
Bear Mountain, BC
Year:
2017
Client:
BC Hydro
Partnered with:
SNC Lavalin
Scope of Work:
Installation of 4 230/138kV Circuit
Breaker/Disconnects, 230/138kV 150MVA Transformer,
138kV 30MVAR Capacitor Bank.
Testing & Commissioning of all new and modified Protection & Control, SCADA

BC Hydro – CBK IT Project

Location:
Cranbrook, BC
Year:
2016
Client:
BC Hydro
Scope of Work:
500kV Stand Alone CT replacements
12kV-240kV-500kV voltage transformer replacements
240kV Dead Tank breaker replacement
Testing and Commissioning of all related P&C and SCADA

BC Hydro – Steeples substation 25kV Breaker Replacement

Location:
Cranbrook, BC
Year:
2016
Client:
BC Hydro
Scope of Work:
Testing and Commissioning of all P&C and SCADA

Kineticor – Turbine Skids

Location:
Shaunavon, SK
Year:
2016
Client:
Kineticor
Scope of Work:
Commissioning of 480V/25kV turbine skid package
Set and testing of 25kV recloser
Integration of turbine signals to switchgear/function testing

AltaLink – Bowmanton Station Upgrade

Location:
Bowmanton, AB
Year:
2016
Client:
AltaLink
Partnered with:
ABB
Scope of Work:
Develop grounding plan for 240kV and 138kV substation
Installation of protective grounds for substation work

AltaLink – 244s North Red Deer Station Upgrade

Location:
Red Deer, AB
Year:
2016
Client:
AltaLink
Partnered with:
SNC Lavalin
Scope of Work:
Relocation of 138kV line protections
Demolition/installation of 4x protection relay modules (311C/311L/D60/L90)
Test and Commission relays/CT circuits
End to End Testing with Remote Substations

AltaLink – 28s West Brooks Station Upgrade Project

Location:
Brooks, AB
Year:
2016
Client:
AltaLink
Scope of Work:
Installation, Commissioning, and Acceptance of new Battery Bank
SCADA configuration changes to update new alarms to control center
Divided entire substation PY and SY PN’s
DC loads between the two Battery Banks while maintaining Critical DC Load.

AltaLink – 520s Bennett Station Project

Location:
Calgary, AB
Year:
2015
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
500kV & 240 Breaker Commissioning
500kV Transformer Commissioning
500kV CVT/PT/MOD Commissioning
240kV CVT/PT/MOD Commissioning

AltaLink – Langdon Crossings Station Upgrade Project

Location:
Crossings, AB
Year:
2015
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Protection and Control Racks Commissioning
End to End Testing with Remote Substations
SCADA Commissioning
Interconnection between 500kV AC and DC Converter Stations

AltaLink – 74s Janet Station Upgrade Project

Location:
Langdon, AB
Year:
2015
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

AltaLink – 320p Keephills Station Upgrade Project

Location:
Jasper, AB
Year:
2015
Client:
AltaLink
Scope of Work:
SCADA Commissioning Phase II

AltaLink – 356s Milo Station Upgrade Project

Location:
Milo, AB
Year:
2015
Client:
AltaLink
Scope of Work:
Protection and Control Rack Commissioning
SCADA Commissioning
End to End Testing with Remote Ends

AltaLink – 262s Rocky Mountain Station Upgrade Project

Location:
Mountain House, AB
Year:
2015
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Commissioning of 2 sets of new Stand Alone 138kV CT’s
Demolition and upgrade of existing 138kV Bus Protection to GE-B30 PN
Install and Commission new SEL-2440 SEL status boards

AltaLink – 217s SunnyBrook Station Upgrade Project

Location:
Stony Plain, AB
Year:
2015
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Protection and Control Racks Commissioning
End to End Testing with Remote Substations
SCADA Commissioning
Interconnection between 500kV AC and DC Converter Stations.

AltaLink – 28s West Brooks Station Upgrade Project

Location:
Brooks, AB
Year:
2015
Client:
AltaLink
Scope of Work:
Commissioning new Stand Alone 138kV CT’s
Install and Commission new ABB Switchsync
F236 POW controller for existing 240kV Shunt Reactor

AltaLink – 223s Strome Station Upgrade Project

Location:
Strome, AB
Year:
2015
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 332s Ellis Station Upgrade Project

Location:
Taber, AB
Year:
2013
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

AltaLink – 535s Joffre Station Upgrade Project

Location:
Joffre, AB
Year:
2013
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

AltaLink – 276s Prentiss Station Upgrade Project

Location:
Buffalo Lake, AB
Year:
2013
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

AltaLink – 520s Temporary Bennett Station Project

Location:
Calgary, AB
Year:
2013
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
500kV & 240 Breaker Commissioning
500kV Transformer Commissioning
500kV CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 132s Ware Junction Station Upgrade Project

Location:
Mount Ware, AB
Year:
2013
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning

AltaLink – 17s Benalto Station Upgrade

Location:
Benalto, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

AltaLink – 520s Benalto Station Upgrade

Location:
Benalto, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
500kV & 240kV Breaker Commissioning
500kV CVT/PT/MOD Commissioning
500kV Transformer Commissioning
Protection and Control Racks Commissioning

AltaLink – 324s Cassils and 244s Bowmanton Station Upgrade

Location:
Bowmanton, AB
Year:
2012
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138kV & 240kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 535s Joffre Station Upgrade

Location:
Joffre, AB
Year:
2012
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

BC Hydro – Invermere Substation Upgrade

Location:
Invermere, BC
Year:
2012
Client:
BC Hydro
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

BC Hydro – Long Lake Terminal Substation Upgrade

Location:
Long Lake, BC
Year:
2012
Client:
BC Hydro
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

BC Hydro – Maryville Substation Upgrade

Location:
Maryville, BC
Year:
2012
Client:
BC Hydro
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

BC Hydro – Natal Substation Upgrade

Location:
Sparwood, BC
Year:
2012
Client:
BC Hydro
Partnered with:
AltaLink
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

AltaLink – 574s Nilrem Station Project

Location:
Provost, AB
Year:
2012
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
25kV & 138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 217s North Red Deer Station Upgrade

Location:
Red Deer, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

AltaLink – 120s Picture Butte Station Upgrade

Location:
Picture Butte, AB
Year:
2012
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

AltaLink – 768s Rowley Station Upgrade

Location:
Rowley, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV & 240kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

BC Hydro – Skeena Substation Upgrade

Location:
Skeena, AB
Year:
2012
Client:
BC Hydro
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

AltaLink – 478s Tucuman Substation Upgrade

Location:
Tucuman, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
25kV Switchgear Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 54s Westwood Station Upgrade

Location:
Fort Saskatchewan, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
25kV & 138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

AltaLink – 28s West Brooks Substation Upgrade

Location:
Brooks, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

BC Hydro – Athalmer and Radium Upgrade

Location:
Athalmer and Radium, BC
Year:
2012
Client:
BC Hydro
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

AltaLink – 58s Edson Substation Project

Location:
Edson, AB
Year:
2012
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

AltaLink – 28s West Brooks Upgrade

Location:
Brooks, AB
Year:
2012
Client:
AltaLink
Scope of Work:
Protection and Controls (Brownfield)
SCADA Commissioning

AltaLink – AltaLink Hardisty Upgrade

Location:
Hardisty, AB
Year:
2011
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
Commissioning if POW breaker and CAP bank
CVT/PT/MOD Commissioning
Protection and Controls (Brownfield)
SCADA Commissioning

AltaLink – 723s Christina Lake Substation Project

Location:
Christina Lake, AB
Year:
2011
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Transformer Commissioning

AltaLink – Tucuman/Hardisty Upgrade

Location:
Hardisty, AB
Year:
2011
Client:
AltaLink
Partnered with:
Clearstream Energy
Scope of Work:
Commissioning 138kV Transformer
Commissioning 25kV Transformer
CVT/PT/MOD Commissioning
Protection and Controls (Brownfield)

AltaLink – 51s Wainwright Substation Project

Location:
Wainright, AB
Year:
2011
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Transformer Commissioning

AltaLink – 562s Cypress Substation Project

Location:
Cypress, AB
Year:
2010
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

AltaLink – 186s DryCreek & 199s East Airdrie Substation Upgrade

Location:
Airdrie, AB
Year:
2010
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Cap Bank Commissioning
25kV Switchgear Commissioning

AltaLink – 406s Fickle Lake Substation Upgrade

Location:
Fickle Lake, AB
Year:
2010
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Transformer Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Protection and Control Racks Commissioning

AltaLink – 59s Peigan Substation Upgrade

Location:
Peigan, AB
Year:
2010
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing of Relays with Remote End Substations

AltaLink – 198s Blackfalds Substation Upgrade

Location:
Blackfalds, AB
Year:
2009
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning

AltaLink – Jenner Substation Upgrade

Location:
Jenner, AB
Year:
2009
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Relay Testing with Remote End Substations

AltaLink – 580s Sylvan Lake Substation Upgrade

Location:
Sylvan Lake, AB
Year:
2009
Client:
AltaLink
Partnered with:
Iconic Power Systems
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Protection and Control Racks Commissioning

AltaLink – 28s West Brooks Substation Upgrade

Location:
Brooks, AB
Year:
2009
Client:
AltaLink
Partnered with:
Allteck
Scope of Work:
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning