Complete SCADA Upgrade / Replacement

Location:
AltaLink 320P Keephills
End User:
AltaLink
Year/ Duration:
2017/2018
Scope of Work:
Demolition and cut over of old D20 SCADA system, Annunciator, Alarms, supervisory controls and analogs to new standardized SCADA system.
Multiple Outages staged systematically to cut over 320P Substation until the entire substation complete.
Demolition of metering transducers and installation of new SCADA meters.
Demolition and cut over of old station LAN and IRIG-B clocks to new standard LAN equipment and IRIG-B clocks

FNE Station Replacement Project

Location:
BC Hydro Natal & Eiko Substations
End User:
BC Hydro/AMEC
Year/ Duration:
2017-2018 / 3mos
Scope of Work:
60kV Line Protection replacements including Testing & Commissioning

Manitoba Hydro Bi-pole 3 Project 500kV HVDC

Location:
Riel Station, Winnipeg
End User:
Siemens AG & Mortenson Construction
Year/ Duration:
2017-2018
Scope of Work:
Equipment pre-commissioning for HVDC yard, 240kV AC filter banks, DC Charger and UPS systems, and low voltage auxiliary power systems.
Coordination with construction to assist in the gas filling for HVDC voltage dividers.
Client Support with energization procedures, switching, and LOTO of LV auxiliary power system.

BMT Load Capacity Increase Project

Location:
BC Hydro Bear Mountain Terminal Substation
End User:
BC Hydro / SNC Lavalin
Year/ Duration:
2017
Scope of Work:
Provide on-site Technical support for installation of 4 230/138kV Circuit Breaker/Disconnects, 230/138kV 150MVA Transformer, 138kV 30MVar Capacitor Bank.
Testing & Commissioning of all new and modified Protection & Control, SCADA and Automation systems and equipment.

Complete SCADA Upgrade / Replacement

Location:
AltaLink 89S Ellersile
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Demolition and cut over of old D20 SCADA system, Annunciator, Alarms, supervisory controls and analogs to new standardized SCADA system.
Multiple Outages staged systematically to cut over 89S Substation until the entire substation complete.
Demolition of mimic board and metering transducers, replacement of 240KV Airbreak control modules. Installation of new SCADA meters.
Demolition and cut over of old station LAN and IRIG-B clocks to new standard LAN equipment and IRIG-B clocks

Altalink RATD project

Location:
AltaLink RedDeer 63s; Innisfail 214s; Hazelwood 287s
End User:
SNC
Year/ Duration:
2017
Scope of Work:
Full Green Field Commissioning of Hazelwood Substation
Demo/Install of line/Transformer/Bus Protection in Remote Ends
Testing and Commissioning of all Major Equipment
Testing and Commissioning of all P&C and SCADA Equipment

SCADA Upgrade / Urgent Replacement

Location:
AltaLink 395S North Holden
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Urgent replacement/retrofit of failed of failed D20++ with a D20 EME

RATD Phase 3

Location:
AltaLink Ellis 332s
End User:
SNC
Year/ Duration:
2017
Scope of Work:
Transmission line addition and lines swapped
Bus Protection upgrade
138KV dead tank breaker commissioning
Airbreak and Surge Arresters commissioning

Complete SCADA Upgrade / Replacement

Location:
AltaLink 793s Horse Creek
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Demolition and cut over of old D20 SCADA system, Annunciator, Alarms & supervisory controls to new standardized SCADA system.
Multiple Outages staged systematically to cut over 793s Substation until the entire substation and integration with IPL plant was complete.
T1, T2, & T3 Airbreak control modules, and meter transducers were upgraded.
Existing 138 Bus differential upgraded from High impedance protection to new digital differential protection.

65s High River 25kV Breaker Replacements

Location:
AltaLink 65s High River
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Coordination with AML substation crews to assist in the P&C changes and Equipment commissioning for the replacements of Qty - 4 25kV Outdoor Circuit Breakers.

SCADA Upgrade / Urgent Replacement

Location:
AltaLink 395S North Holden
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Urgent replacement/retrofit of failed of failed D20++ with a D20 EME

352s Onoway 69kV Breaker Replacement

Location:
AltaLink 352s Onoway
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Coordination with AML scheduling / AML Mobile Sub Crew/ Construction and Commissioning for the installation of the Mobile Substation
Salvage of existing 69kV Bulk Oil breaker and installation of new Mitsubishi 69kV Dead Tank BKR.
Salvage and Replacement of existing 69kV Hook switches
Installation of new Line Side Surge Arrestors.

649s Full Metering Upgrade

Location:
AltaLink 649s Chapice Lake
End User:
AltaLink
Year/ Duration:
2017
Scope of Work:
Addition of Single Phase 138kV Metering PT to change existing revenue metering scheme from a 2 PT Metering Method to 3 phase Metering Method.
Energization support – Load Readings / Phasing Checks

Keewatinohk AC Yard Pre-Commissioning

Location:
Keewatinohk Converter Station AC Yard
End User:
SNC
Year/ Duration:
2017
Scope of Work:
Full Green Field Pre-Commissioning of AC Yard
Testing of All Major Equipment in AC Yard
Testing of Two 13.8kV Switchgear Buildings
Testing of Three 600V OPC Buildings

KCS/RCS HVDC Equipment Commissioning

Location:
Keewatinohk Converter Station/ Riel Converter Station
End User:
Mortenson
Year/ Duration:
2017
Scope of Work:
Full Testing and Commissioning of HVDC Auxiliary Systems
Full Testing and Commissioning of HVDC Yard Equipment

25KV Breaker Replacement

Location:
BC Hydro Steeples Substation
End User:
BC Hydro
Year/ Duration:
2016
Scope of Work:
Testing and Commissioning of all P&C and SCADA

CBK IT Project

Location:
BC Hydro Cranbrook Substation
End User:
BC Hydro
Year/ Duration:
2016
Scope of Work:
500KV Stand Alone CT replacements
12KV-240KV-500KV voltage transformer replacements
240KV Dead Tank breaker replacement
Testing and Commissioning of all related P&C and SCADA

West Brooks Station Upgrade Project

Location:
AltaLink West Brooks 28s Substation
End User:
AltaLink
Year/ Duration:
2016
Scope of Work:
Installation, Commissioning, and Acceptance of new Battery Bank
SCADA configuration changes to update new alarms to control center
Divided entire substation PY and SY PN’s DC loads between the two
Battery Banks while maintaining Critical DC Load.

North Red Deer Station Upgrade

Location:
AltaLink North Red Deer 217s Substation
End User:
SNC
Year/ Duration:
2016
Scope of Work:
Relocation of 138kV line protections
Demolition/installation of 4x protection relay modules (311C/311L/D60/L90)
Test and Commission relays/CT circuits
End to End Testing with Remote Substations

Bowmanton Station Upgrade

Location:
AltaLink Bowmanton 244s Substation
End User:
ABB/AML
Year/ Duration:
2016
Scope of Work:
Develop grounding plan for 240kV and 138kV substation
Installation of protective grounds for substation work

West Brooks Station Upgrade Project

Location:
AltaLink West Brooks 28s Substation
End User:
AltaLink
Year/ Duration:
2015
Scope of Work:
Commissioning new Stand Alone 138kV CT’s
Install and Commission new ABB Switchsync F236 POW controller for existing 240kV Shunt Reactor

SunnyBrook Station Upgrade Project

Location:
Stoney Plains, ABAltaLink SunnyBrook Substation, Stony Plain, AB
End User:
Allteck/AML
Year/ Duration:
2015
Scope of Work:
Protection and Control Racks Commissioning
End to End Testing with Remote Substations
SCADA Commissioning
Interconnection between 500kV AC and DC Converter Stations.

Rocky Mountain Station Upgrade Project

Location:
AltaLink Rocky Mountain House 262s Substation
End User:
Allteck/AML
Year/ Duration:
2015
Scope of Work:
Commissioning of 2 sets of new Stand Alone 138kV CT’s
Demolition and upgrade of existing 138kV Bus Protection to GE-B30 PN
Install and Commission new SEL-2440 SEL status boards

Milo Station Upgrade Project

Location:
AltaLink Milo 356s Substation, AB
End User:
AltaLink/AML
Year/ Duration:
2015
Scope of Work:
Protection and Control Rack Commissioning
SCADA Commissioning
End to End Testing with Remote Ends

Keephills Station Upgrade Project

Location:
AltaLink Keephills 320P Substation
End User:
AltaLink
Year/ Duration:
2015
Scope of Work:
SCADA Commissioning Phase II

Janet Station Upgrade Project

Location:
AltaLink Janet 74s Substation
End User:
Iconic Power
Year/ Duration:
2015
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

Crossings Station Upgrade Project

Location:
AltaLink Langdon Substation, Crossings, AB
End User:
Allteck/AML
Year/ Duration:
2015
Scope of Work:
Protection and Control Racks Commissioning
End to End Testing with Remote Substations
SCADA Commissioning
Interconnection between 500kV AC and DC Converter Stations.

Bennett Station Project

Location:
AltaLink Bennett 520s Substation
End User:
Allteck
Year/ Duration:
2015
Scope of Work:
500kV & 240 Breaker Commissioning
500kV Transformer Commissioning
500kV CVT/PT/MOD Commissioning
240kV CVT/PT/MOD Commissioning

Strome Station Upgrade Project

Location:
AltaLink Strome 223s Substation
End User:
AltaLink
Subcontracted:
URS Flint
Year/ Duration:
2014/2015
Scope of Work:
138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Ware Junction Station Upgrade Project

Location:
AltaLink Ware Junction 132s Substation
End User:
Allteck
Year/ Duration:
2013
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning

Temporary Bennett Station Project

Location:
AltaLink Bennett 520s Substation
End User:
Allteck
Year/ Duration:
2013
Scope of Work:
500kV & 240 Breaker Commissioning
500kV Transformer Commissioning
500kV CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Prentiss Station Upgrade Project

Location:
AltaLink Prentiss 276s Substation
End User:
URS Flint
Year/ Duration:
2013
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

Joffre Station Upgrade Project

Location:
AltaLink Joffre 535s Substation
End User:
URS Flint
Year/ Duration:
2013
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

Ellis Station Upgrade Project

Location:
AltaLink Ellis 332s Substation
End User:
URS Flint
Year/ Duration:
2013
Scope of Work:
138kV Breaker Commissioning with POW
CVT/PT/MOD Commissioning
Cap bank Commissioning
Protection and Control Racks Commissioning

Benalto Station Upgrade

Location:
AltaLink Benalto 17s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

West Brooks Substation Upgrade

Location:
AltaLink West Brooks 28s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Westwood Station Upgrade

Location:
AltaLink Westwood 054s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
25kV & 138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Tucuman Substation Upgrade

Location:
AltaLink Tucuman 478s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
25kV Switchgear Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Skeena Substation Upgrade

Location:
BC Hydro Skeena Substation
End User:
BC Hydro
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Rowley Station Upgrade

Location:
Atco Rowley 768s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
138kV & 240kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Picture Butte Station Upgrade

Location:
AltaLink Picture Butte 120s Substation
End User:
AltaLink
Subcontracted:
URS Flint
Year/ Duration:
2012
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

North Red Deer Station Upgrade

Location:
AltaLink North Red Deer 217s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing with Remote Substations

Nilrem Station Project

Location:
AltaLink Nilrem 574s Substation
End User:
USR Flint
Year/ Duration:
2012
Scope of Work:
25kV & 138kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Natal Substation Upgrade

Location:
BC Hydro Natal Substation
End User:
BC Hydro
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Maryville Substation Upgrade

Location:
BC Hydro Maryville Substation
End User:
BC Hydro
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Long Lake Terminal Substation Upgrade

Location:
BC Hydro Long Lake Terminal Substation
End User:
BC Hydro
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Invermere Substation Upgrade

Location:
BC Hydro Invermere Substation
End User:
BC Hydro
Year/ Duration:
2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Joffre Station Upgrade

Location:
AltaLink Joffre 535s Substation
End User:
URS Flint
Year/ Duration:
2012
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

Cassils and Bowmanton Station Upgrade

Location:
AltaLink Cassils 324s and Bowmanton 244s Substation
End User:
Iconic Power Systems
Year/ Duration:
2012
Scope of Work:
138kV & 240kV Breaker Commissioning
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning

Benalto Station Upgrade

Location:
AltaLink Temp Bennett 520s Substation
End User:
Allteck
Year/ Duration:
2012
Scope of Work:
500kV & 240kV Breaker Commissioning
500kV CVT/PT/MOD Commissioning
500kV Transformer Commissioning
Protection and Control Racks Commissioning

Wainwright Substation Project

Location:
AltaLink Wainright 51s Substation
End User:
Allteck
Year/ Duration:
2011
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Transformer Commissioning

Tucuman/Hardisty Upgrade

Location:
Altalink Tucuman/Hardisty, AB
End User:
USR Flint
Year/ Duration:
2011
Scope of Work:
Commissioning 138kV Transformer
Commissioning 25kV Transformer
CVT/PT/MOD Commissioning
Protection and Controls (Brownfield)

Christina Lake Substation Project

Location:
AltaLink Christina Lake 723s Substation
End User:
Allteck
Year/ Duration:
2011
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Transformer Commissioning

AltaLink Hardisty Upgrade

Location:
Altalink Hardisty, AB
End User:
USR Flint
Year/ Duration:
2011
Scope of Work:
Commissioning if POW breaker and CAP bank
CVT/PT/MOD Commissioning
Protection and Controls (Brownfield)
SCADA Commissioning

West Brooks Upgrade

Location:
Altalink West Brooks 28s, AB
End User:
AltaLink
Year/ Duration:
2011/2012
Scope of Work:
Protection and Controls (Brownfield)
SCADA Commissioning

Edson Substation Project

Location:
AltaLink Edson 58s Substation
End User:
Allteck
Year/ Duration:
2011/2012
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

Athalmer and Radium Upgrade

Location:
Athalmer and Radium Substations, BC
End User:
BC Hydro
Year/ Duration:
2011/2012
Scope of Work:
Protection and Control Racks Commissioning
SCADA Commissioning

Peigan Substation Upgrade

Location:
AltaLink Peigan 59s Substation
End User:
Allteck
Year/ Duration:
2010
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Testing of Relays with Remote End Substations

Fickle Lake Substation Upgrade

Location:
AltaLink Fickle Lake 406s Substation
End User:
Allteck
Year/ Duration:
2010
Scope of Work:
Transformer Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Protection and Control Racks Commissioning

Dry Creek & East Airdrie Substation Upgrade

Location:
AltaLink DryCreek 186s/East Airdrie 199s Substation
End User:
Iconic Power Systems
Year/ Duration:
2010
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Cap Bank Commissioning
25kV Switchgear Commissioning

Cypress Substation Project

Location:
AltaLink Cypress 562s Substation
End User:
Allteck
Year/ Duration:
2010
Scope of Work:
138kV & 240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Transformer Commissioning
Protection and Control Racks Commissioning

West Brooks Substation Upgrade

Location:
AltaLink WestBrooks 28s Substation
End User:
Allteck
Year/ Duration:
2009
Scope of Work:
Transformer Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning

Sylvan Lake Substation Upgrade

Location:
AltaLink Sylvan Lake 580s Substation
End User:
Iconic Power Systems
Year/ Duration:
2009
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
25kV Switchgear Commissioning
Protection and Control Racks Commissioning

Jenner Substation Upgrade

Location:
AltaLink Jenner 275s Substation
End User:
Allteck
Year/ Duration:
2009
Scope of Work:
240kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
End to End Relay Testing with Remote End Substations

Blackfalds Substation Upgrade

Location:
AltaLink Blackfalds 198s Substation
End User:
Allteck
Year/ Duration:
2009
Scope of Work:
138kV Breaker Commissioning
CVT/PT/MOD Commissioning
Protection and Control Racks Commissioning
SCADA Commissioning

Bear Mountain Wind

Location:
Bear Mountain Wind IPP, BC
End User:
AltaGas/Iconic Power
Year/ Duration:
2009
Scope of Work:
Commissioning of 138kV breakers
Commissioning transformer
Protection and Control Racks Commissioning
SCADA Commissioning

Sunnybrook 510s 40V Breaker Addition

Location:
Sunnybrook 510s Substation
End User:
Burns & McDonnel/Altalink
Year/ Duration:
July 2018
Scope of Work:
480V Breaker Addition to existing Switchgear
Application of protection settings
Final Testing and Commissioning